Flag City Solar
BetaActiveSolarERCOTLBNL
167.3 MW generation in Jackson, TX · In queue since May 2019 · Proposed COD December 2026
167.3 MW
Capacity
1
Components
Solar
6y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 7m
Facilities Study50%
Queue EntryMay 7, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Jackson
Region
ERCOT
Developer
Flag City Solar Project, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 5588 Red Bluff - 5546 Danevang c1
Data Source
LBNL
No news available for this project.