Flag City Solar — Project Summary

Queue ID
ERCOT-21INR0343
Capacity
167.3 MW
Technology
Solar
Status
active
Location
Jackson, TX
Region
ERCOT
Developer
Flag City Solar Project, LLC
IA Status
Facility Study

Flag City Solar

BetaActiveSolarERCOTLBNL

167.3 MW generation in Jackson, TX · In queue since May 2019 · Proposed COD December 2026

167.3 MW

Capacity

1

Components

Solar

6y 10m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 7m

Facilities Study50%
Queue EntryMay 7, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Jackson

Region

ERCOT

Developer

Flag City Solar Project, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 5588 Red Bluff - 5546 Danevang c1

Data Source

LBNL

No news available for this project.