Dove Run Solar
ERCOT-21INR0326BetaActiveSolarERCOTLBNL + Live
120.86 MW generation in Duval, TX · In queue since May 2019 · Proposed COD October 2027
120.86 MW
Capacity
1
Components
Solar
6y 11m
In Queue
IA Executed
IA Status
Signed Oct 2023
Interconnection Timeline
Queue → IA
4y 5m
IA → COD
4 years
Total Duration
4y 5m
Construction75%
Queue EntryMay 7, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 31, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-10-15
Project Details
State
TX
County
Duval
Region
ERCOT
Developer
Dove Run Solar Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 138kV 8510 Falfurrias - 8695 Crestonio
Data Source
LBNL + Live