Dove Run Solar — Project Summary

Queue ID
ERCOT-21INR0326
Capacity
120.86 MW
Technology
Solar
Status
active
Location
Duval, TX
Region
ERCOT
Developer
Dove Run Solar Project, LLC
IA Status
IA Executed

Dove Run Solar

ERCOT-21INR0326BetaActiveSolarERCOTLBNL + Live

120.86 MW generation in Duval, TX · In queue since May 2019 · Proposed COD October 2027

120.86 MW

Capacity

1

Components

Solar

6y 11m

In Queue

IA Executed

IA Status

Signed Oct 2023

Interconnection Timeline

Queue → IA

4y 5m

IA → COD

4 years

Total Duration

4y 5m

Construction75%
Queue EntryMay 7, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 31, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-10-15

Project Details

State

TX

County

Duval

Region

ERCOT

Developer

Dove Run Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 138kV 8510 Falfurrias - 8695 Crestonio

Data Source

LBNL + Live

No news available for this project.