Board Creek Wind — Project Summary

Queue ID
ERCOT-21INR0324
Capacity
299.2 MW
Technology
Wind
Status
active
Location
Navarro, TX
Region
ERCOT
Developer
Limestone Wind Project, LLC
IA Status
IA Executed

Board Creek Wind

ERCOT-21INR0324BetaActiveWindERCOTLBNL + Live

299.2 MW generation in Navarro, TX · In queue since April 2019 · Proposed COD April 2026

299.2 MW

Capacity

1

Components

Wind

7 years

In Queue

IA Executed

IA Status

Signed Aug 2021

Interconnection Timeline

Queue → IA

2y 4m

IA → COD

4y 8m

Total Duration

2y 4m

Construction75%
Queue EntryApr 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 19, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-04-30

Project Details

State

TX

County

Navarro

Region

ERCOT

Developer

Limestone Wind Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

345kV 3386 Outlaw Switch

Data Source

LBNL + Live

No news available for this project.