Board Creek Wind
ERCOT-21INR0324BetaActiveWindERCOTLBNL + Live
299.2 MW generation in Navarro, TX · In queue since April 2019 · Proposed COD April 2026
299.2 MW
Capacity
1
Components
Wind
7 years
In Queue
IA Executed
IA Status
Signed Aug 2021
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
4y 8m
Total Duration
2y 4m
Construction75%
Queue EntryApr 24, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementAug 19, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-04-30
Project Details
State
TX
County
Navarro
Region
ERCOT
Developer
Limestone Wind Project, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV 3386 Outlaw Switch
Data Source
LBNL + Live