Ion Solar
BetaActiveSolarERCOTLBNL
384 MW generation in Ellis, TX · In queue since May 2019 · Proposed COD May 2026
384 MW
Capacity
1
Components
Solar
6y 10m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7 years
Facilities Study50%
Queue EntryMay 17, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-05-29
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
GSE Group LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 1906 Venus - 68091 Navarro
Data Source
LBNL
No news available for this project.