Mandorla Solar
BetaSuspendedSolarERCOTLBNL
254 MW generation in Milam, TX · In queue since January 2020
254 MW
Capacity
1
Components
Solar
6y 2m
In Queue
IA Executed
IA Status
Signed Sep 2022
Interconnection Timeline
Queue → IA
2y 8m
Total Duration
2y 8m
Suspended75%
Queue EntryJan 22, 2020
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 19, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Milam
Region
ERCOT
Developer
Ben Milam Solar 2
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 3687 Bell E - 39950 TNTNP One, one-half from Bell
Data Source
LBNL
No news available for this project.