Sterling Prairie Solar
BetaActiveSolarERCOTLBNL
119.91 MW generation in Matagorda, TX · In queue since April 2019 · Proposed COD December 2025
119.91 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
6y 8m
Schedule
3 months past proposed COD
Facilities Study50%
Queue EntryApr 24, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-15
Project Details
State
TX
County
Matagorda
Region
ERCOT
Developer
RWE Solar Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
8608 Pavlov A 138kV
Data Source
LBNL