Sterling Prairie Solar — Project Summary

Queue ID
ERCOT-21INR0295
Capacity
119.91 MW
Technology
Solar
Status
active
Location
Matagorda, TX
Region
ERCOT
Developer
RWE Solar Development, LLC
IA Status
Facility Study

Sterling Prairie Solar

BetaActiveSolarERCOTLBNL

119.91 MW generation in Matagorda, TX · In queue since April 2019 · Proposed COD December 2025

119.91 MW

Capacity

1

Components

Solar

6y 11m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

6y 8m

Schedule

3 months past proposed COD

Facilities Study50%
Queue EntryApr 24, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-15

Project Details

State

TX

County

Matagorda

Region

ERCOT

Developer

RWE Solar Development, LLC

Utility

Entity

ERCOT

Point of Interconnection

8608 Pavlov A 138kV

Data Source

LBNL

No news available for this project.