Mountaineer Solar
BetaActiveSolarERCOTLBNL + Live
329.64 MW generation in Brown, TX · In queue since April 2019 · Proposed COD November 2028
329.64 MW
Capacity
1
Components
Solar
6y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 7m
Facilities Study50%
Queue EntryApr 16, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-11-01
Project Details
State
TX
County
Brown
Region
ERCOT
Developer
Mustang Mountaineer Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1444 Brown 345 kV
Data Source
LBNL + Live
No news available for this project.