Edgewater Storage
BetaActiveBatteryERCOTLBNL + Live
50 MW storage in Ellis, TX · In queue since April 2019 · Proposed COD February 2028
50 MW
Capacity
1
Components
Battery
6y 11m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
8y 10m
Facilities Study50%
Queue EntryApr 8, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-29
Project Details
State
TX
County
Ellis
Region
ERCOT
Developer
Edgewater Battery Storage LLC
Utility
—
Entity
ERCOT
Point of Interconnection
210 Reagor Springs 69kV
Data Source
LBNL + Live