Edgewater Storage — Project Summary

Queue ID
ERCOT-21INR0280
Capacity
50 MW
Technology
Battery
Status
active
Location
Ellis, TX
Region
ERCOT
Developer
Edgewater Battery Storage LLC
IA Status
Facility Study

Edgewater Storage

BetaActiveBatteryERCOTLBNL + Live

50 MW storage in Ellis, TX · In queue since April 2019 · Proposed COD February 2028

50 MW

Capacity

1

Components

Battery

6y 11m

In Queue

Facility Study

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

8y 10m

Facilities Study50%
Queue EntryApr 8, 2019

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-02-29

Project Details

State

TX

County

Ellis

Region

ERCOT

Developer

Edgewater Battery Storage LLC

Utility

Entity

ERCOT

Point of Interconnection

210 Reagor Springs 69kV

Data Source

LBNL + Live

No news available for this project.