Fighting Jays Solar
351.29 MW generation in Fort Bend, TX · In queue since March 2019 · Proposed COD March 2025
351.29 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
Signed Jun 2020
Queue → IA
1y 3m
IA → COD
4y 9m
Total Duration
1y 3m
Schedule
12 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-03-29
State
TX
County
Fort Bend
Region
ERCOT
Developer
AP Solar Holdings, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 44000 WA Parish - 44200 Hillje c64
Data Source
LBNL