Greyhound Solar
587.76 MW generation in Ector, TX · In queue since March 2019 · Proposed COD March 2026
587.76 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
Signed Jan 2022
Queue → IA
2y 10m
IA → COD
4y 2m
Total Duration
2y 10m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-31
State
TX
County
Ector
Region
ERCOT
Developer
Rockhound Solar 2, LLC dba "Greyhound Solar"
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
Tap 345kV 11010 Wolf - 1018 Moss
Data Source
LBNL + Live