Sisters Solar
ERCOT-21INR0265BetaActiveSolarERCOTLBNL + Live
301.6 MW generation in Ector, TX · In queue since February 2019 · Proposed COD February 2028
301.6 MW
Capacity
1
Components
Solar
7y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9 years
Facilities Study50%
Queue EntryFeb 28, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-02-21
Project Details
State
TX
County
Ector
Region
ERCOT
Developer
Oberon Solar LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tapping the 345 kV line connecting Moss Switch (Bus# 1018) to Wolf Switching Station (Bus# 11010)
Data Source
LBNL + Live