Horizon Solar
BetaSuspendedSolarERCOTLBNL
204.09 MW generation in Frio, TX · In queue since March 2019
204.09 MW
Capacity
1
Components
Solar
7 years
In Queue
IA Executed
IA Status
Signed Jul 2019
Interconnection Timeline
Queue → IA
4 months
Total Duration
4 months
Suspended75%
Queue EntryMar 5, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJul 12, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 12–24 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Frio
Region
ERCOT
Developer
Horizon Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5897 Horizon Switch 138kV
Data Source
LBNL
No news available for this project.