Amsterdam Solar
509.88 MW generation in Brazoria, TX · In queue since February 2019 · Proposed COD February 2026
509.88 MW
Capacity
1
Components
Solar
7y 1m
In Queue
IA Executed
IA Status
Signed Feb 2022
Queue → IA
3 years
IA → COD
4 years
Total Duration
3 years
Schedule
2 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-02-01
State
TX
County
Brazoria
Region
ERCOT
Developer
Cottonwood Bayou Solar II, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 43035 Oasis - 42500 Dow c27, c18
Data Source
LBNL