Adamstown Solar — Project Summary

Queue ID
ERCOT-21INR0210
Capacity
251.28 MW
Technology
Solar
Status
active
Location
Wichita, TX
Region
ERCOT
Developer
Adams Creek Solar Project, LLC
IA Status
IA Executed

Adamstown Solar

ERCOT-21INR0210BetaActiveSolarERCOTLBNL + Live

251.28 MW generation in Wichita, TX · In queue since November 2018 · Proposed COD August 2027

251.28 MW

Capacity

1

Components

Solar

7y 5m

In Queue

IA Executed

IA Status

Signed Aug 2022

Interconnection Timeline

Queue → IA

3y 9m

IA → COD

5 years

Total Duration

3y 9m

Construction75%
Queue EntryNov 20, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 8, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-08-31

Project Details

State

TX

County

Wichita

Region

ERCOT

Developer

Adams Creek Solar Project, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 1730 West Krum - 6111 Riley Ckt 2

Data Source

LBNL + Live