Eastbell Milam Solar
244.86 MW generation in Milam, TX · In queue since October 2018 · Proposed COD October 2025
244.86 MW
Capacity
1
Components
Solar
7y 6m
In Queue
IA Executed
IA Status
Signed Sep 2022
Queue → IA
3y 11m
IA → COD
3y 1m
Total Duration
3y 11m
Schedule
5 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-10-31
State
TX
County
Milam
Region
ERCOT
Developer
EDP RENEWABLES NORTH AMERICA LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345 kV Bell County East Switch (bus# 3687) - TNP One (bus# 39950) circuit 2
Data Source
LBNL + Live