Indigo Solar
150 MW generation in Fisher, TX · In queue since September 2018 · Proposed COD September 2027
150 MW
Capacity
1
Components
Solar
7y 7m
In Queue
IA Executed
IA Status
Signed Sep 2022
Queue → IA
4 years
IA → COD
5 years
Total Duration
4 years
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2027-09-17
State
TX
County
Fisher
Region
ERCOT
Developer
Innovative Solar 245, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345 kV 68001 Claytonville _x0013_ 68004 Phantom Hill Circuit 2