Red Holly Solar — Project Summary

Queue ID
ERCOT-21INR0022
Capacity
260 MW
Technology
Solar
Status
active
Location
Dawson, TX
Region
ERCOT
Developer
GreenGo Energy
IA Status
IA Executed

Red Holly Solar

ERCOT-21INR0022BetaActiveSolarERCOTLBNL + Live

260 MW generation in Dawson, TX · In queue since July 2018 · Proposed COD June 2027

260 MW

Capacity

1

Components

Solar

7y 9m

In Queue

IA Executed

IA Status

Signed Oct 2020

Interconnection Timeline

Queue → IA

2y 3m

IA → COD

6y 8m

Total Duration

2y 3m

Construction75%
Queue EntryJul 11, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementOct 19, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2027-06-01

Project Details

State

TX

County

Dawson

Region

ERCOT

Developer

GreenGo Energy

Utility

Entity

ERCOT

Service Type

Point of Interconnection

tap 345kV 59900 Longdraw - 79641 Farmland

Data Source

LBNL + Live

No news available for this project.