Air Products GCA
14 MW generation in Galveston, TX · In queue since June 2018 · Proposed COD December 2025
14 MW
Capacity
1
Components
Gas
7y 10m
In Queue
IA Executed
IA Status
Signed Aug 2020
Queue → IA
2y 2m
IA → COD
5y 4m
Total Duration
2y 2m
Schedule
3 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 24–48 months
Proposed COD: 2025-12-31
State
TX
County
Galveston
Region
ERCOT
Developer
Air Products
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
39140 TNTxCityMain 69kV (Will be upgraded to 138kV)
Data Source
LBNL + Live
Last updated 2026-03-26