Giddings Wind
BetaActiveWindERCOTLBNL + Live
240 MW generation in Upton, TX · In queue since September 2017 · Proposed COD September 2030
240 MW
Capacity
1
Components
Wind
8y 6m
In Queue
Facility Study
IA Status
COD target: 2030
Interconnection Timeline
Total Duration
13 years
Facilities Study50%
Queue EntrySep 6, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2030-09-09
Project Details
State
TX
County
Upton
Region
ERCOT
Developer
Pioneer Natural Resources
Utility
—
Entity
ERCOT
Point of Interconnection
71212 Upton 138kV
Data Source
LBNL + Live
No news available for this project.