0.5 MW generation in Glasscock, TX · In queue since November 2019 · Proposed COD March 2025
0.5 MW
Capacity
1
Components
Wind
6y 4m
In Queue
IA Executed
IA Status
Signed Nov 2006
Interconnection Timeline
IA → COD
18y 4m
Total Duration
6y 4m
Schedule
13 months past proposed COD
Construction75%
Queue EntryNov 27, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementNov 11, 2006
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-03-01
Project Details
State
TX
County
Glasscock
Region
ERCOT
Developer
RWE Renewables Development, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
1333 McDonald 138kV
Data Source