Greens Bayou Expansion — Project Summary

Queue ID
ERCOT-20INR0267
Capacity
140 MW
Technology
Gas
Status
suspended
Location
Harris, TX
Region
ERCOT
Developer
IA Status

Greens Bayou Expansion

BetaSuspendedGasERCOTLBNL

140 MW generation in Harris, TX

140 MW

Capacity

1

Components

Gas

In Queue

IA Status

Interconnection Timeline
Suspended0%
Queue Entry

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Commercial operation date not yet determined

Project Details

State

TX

County

Harris

Region

ERCOT

Developer

Utility

Entity

ERCOT

Data Source

LBNL

No news available for this project.