Ryan Energy Storage
ERCOT-20INR0246BetaActiveBatteryERCOTLBNL + Live
50 MW storage in Coryell, TX · In queue since January 2019 · Proposed COD December 2026
50 MW
Capacity
1
Components
Battery
7y 3m
In Queue
IA Executed
IA Status
Signed Feb 2021
Interconnection Timeline
Queue → IA
2y 1m
IA → COD
5y 10m
Total Duration
2y 1m
Construction75%
Queue EntryJan 15, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 18, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 6–18 months
Commercial Operation
Proposed COD: 2026-12-12
Project Details
State
TX
County
Coryell
Region
ERCOT
Developer
Ryan Storage LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
37580 TNPancake 69kV
Data Source
LBNL + Live