Anson Solar Center, Phase II — Project Summary

Queue ID
ERCOT-20INR0242
Capacity
200.9 MW
Technology
Solar
Status
active
Location
Jones, TX
Region
ERCOT
Developer
Anson Solar Center 2, LLC
IA Status
IA Executed

Anson Solar Center, Phase II

ERCOT-20INR0242BetaActiveSolarERCOTLBNL + Live

200.9 MW generation in Jones, TX · In queue since June 2017 · Proposed COD March 2026

200.9 MW

Capacity

1

Components

Solar

8y 10m

In Queue

IA Executed

IA Status

Signed Aug 2024

Interconnection Timeline

Queue → IA

7y 2m

IA → COD

1y 7m

Total Duration

7y 2m

Schedule

0 months past proposed COD

Construction75%
Queue EntryJun 23, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 15, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Jones

Region

ERCOT

Developer

Anson Solar Center 2, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

existing tap 345 kV 68004 Phantom Hill station

Data Source

LBNL + Live

Linked EIA Plant

ANSON Solar Center, LLC

EIA Plant ID: 64026

View Plant
No news available for this project.