Anson Solar Center, Phase II
200.9 MW generation in Jones, TX · In queue since June 2017 · Proposed COD March 2026
200.9 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
Signed Aug 2024
Queue → IA
7y 2m
IA → COD
1y 7m
Total Duration
7y 2m
Schedule
0 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2026-03-31
State
TX
County
Jones
Region
ERCOT
Developer
Anson Solar Center 2, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
existing tap 345 kV 68004 Phantom Hill station
Data Source
LBNL + Live
Linked EIA Plant
ANSON Solar Center, LLC
EIA Plant ID: 64026