Crowded Star Solar
ERCOT-20INR0241BetaActiveSolarERCOTLBNL + Live
218.79 MW generation in Jones, TX · In queue since January 2019 · Proposed COD July 2026
218.79 MW
Capacity
1
Components
Solar
7y 3m
In Queue
IA Executed
IA Status
Signed Dec 2019
Interconnection Timeline
Queue → IA
11 months
IA → COD
6y 7m
Total Duration
11 months
Construction75%
Queue EntryJan 21, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 17, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-07-08
Project Details
State
TX
County
Jones
Region
ERCOT
Developer
Jones City Solar, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 68001 Claytonville _x0013_ 68004 Phantom Hill c2
Data Source
LBNL + Live
No news available for this project.