Voyager Storage
BetaActiveBatteryERCOTLBNL + Live
50.14 MW storage in Wharton, TX · In queue since January 2019 · Proposed COD April 2028
50.14 MW
Capacity
1
Components
Battery
7y 2m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
9y 3m
Facilities Study50%
Queue EntryJan 14, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-08
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
EDF Renewables Development, Inc.
Utility
—
Entity
ERCOT
Point of Interconnection
44200 Hillje 345kV
Data Source
LBNL + Live
No news available for this project.