Knickerbocker Solar SLF
BetaActiveSolarERCOTLBNL
241.26 MW generation in Tom Green, TX · In queue since January 2019 · Proposed COD June 2027
241.26 MW
Capacity
1
Components
Solar
7y 2m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
8y 5m
Facilities Study50%
Queue EntryJan 7, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-06-01
Project Details
State
TX
County
Tom Green
Region
ERCOT
Developer
Knickerbocker Solar LLC
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 345kV 76003 Big Hill - 76009 Twin Buttes
Data Source
LBNL