282 MW generation in Lynn, TX · In queue since January 2019 · Proposed COD June 2026
282 MW
Capacity
1
Components
Wind
7y 2m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 5m
Facilities Study50%
Queue EntryJan 11, 2019
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-06-03
Project Details
State
TX
County
Lynn
Region
ERCOT
Developer
Antelope Flats Wind, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
79641 Farmland 345kV