Markum Solar
BetaActiveSolarERCOTLBNL
161.54 MW generation in Mclennan, TX · In queue since December 2018 · Proposed COD April 2025
161.54 MW
Capacity
1
Components
Solar
7y 3m
In Queue
IA Executed
IA Status
Signed Jun 2021
Interconnection Timeline
Queue → IA
2y 6m
IA → COD
3y 10m
Total Duration
2y 6m
Schedule
12 months past proposed COD
Construction75%
Queue EntryDec 18, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 28, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-04-02
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Glory Leasing LLC
Utility
—
Entity
ERCOT
Point of Interconnection
177 Bosque 138kV