Foxtrot Wind
ERCOT-20INR0129BetaActiveWindERCOTLBNL + Live
268.2 MW generation in Bee, TX · In queue since July 2018 · Proposed COD March 2026
268.2 MW
Capacity
1
Components
Wind
7y 9m
In Queue
IA Executed
IA Status
Signed May 2020
Interconnection Timeline
Queue → IA
1y 10m
IA → COD
5y 10m
Total Duration
1y 10m
Schedule
0 months past proposed COD
Construction75%
Queue EntryJul 26, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 5, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
TX
County
Bee
Region
ERCOT
Developer
Lincoln Clean
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
AEP 88689 Tango 345kV station
Data Source
LBNL + Live