Wang Solar SLF — Project Summary

Queue ID
ERCOT-20INR0106
Capacity
144.6 MW
Technology
Solar
Status
active
Location
Falls, TX
Region
ERCOT
Developer
BT Yixin Solar, LLC
IA Status
Facility Study

Wang Solar SLF

BetaActiveSolarERCOTLBNL + Live

144.6 MW generation in Falls, TX · In queue since June 2018 · Proposed COD March 2026

144.6 MW

Capacity

1

Components

Solar

7y 9m

In Queue

Facility Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

7y 9m

Facilities Study50%
Queue EntryJun 14, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-03-31

Project Details

State

TX

County

Falls

Region

ERCOT

Developer

BT Yixin Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 3409 LakeCr1 - 3414 TempSS

Data Source

LBNL + Live

No news available for this project.