Wang Solar SLF
BetaActiveSolarERCOTLBNL + Live
144.6 MW generation in Falls, TX · In queue since June 2018 · Proposed COD March 2026
144.6 MW
Capacity
1
Components
Solar
7y 9m
In Queue
Facility Study
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
7y 9m
Facilities Study50%
Queue EntryJun 14, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-03-31
Project Details
State
TX
County
Falls
Region
ERCOT
Developer
BT Yixin Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 345kV 3409 LakeCr1 - 3414 TempSS
Data Source
LBNL + Live
No news available for this project.