Fagus Solar Park 1 SLF — Project Summary

Queue ID
ERCOT-20INR0091
Capacity
166.42 MW
Technology
Solar
Status
active
Location
Childress, TX
Region
ERCOT
Developer
Excel Advantage Services, LLC dba Misae Solar Park II
IA Status
IA Executed

Fagus Solar Park 1 SLF

ERCOT-20INR0091BetaActiveSolarERCOTLBNL + Live

166.42 MW generation in Childress, TX · In queue since May 2018 · Proposed COD January 2026

166.42 MW

Capacity

1

Components

Solar

7y 11m

In Queue

IA Executed

IA Status

Signed Feb 2019

Interconnection Timeline

Queue → IA

9 months

IA → COD

6y 11m

Total Duration

9 months

Schedule

3 months past proposed COD

Construction75%
Queue EntryMay 15, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementFeb 21, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-01-14

Project Details

State

TX

County

Childress

Region

ERCOT

Developer

Excel Advantage Services, LLC dba Misae Solar Park II

Utility

Entity

ERCOT

Service Type

Point of Interconnection

60501 Tesla 345kV

Data Source

LBNL + Live

No news available for this project.