Baird North Wind
ERCOT-20INR0083BetaActiveWindERCOTLBNL + Live
350 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026
350 MW
Capacity
1
Components
Wind
7y 11m
In Queue
IA Executed
IA Status
Signed May 2019
Interconnection Timeline
Queue → IA
1 year
IA → COD
7y 7m
Total Duration
1 year
Construction75%
Queue EntryMay 4, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementMay 31, 2019
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Callahan
Region
ERCOT
Developer
BMP Wind, LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68008 Latimer 345kV
Data Source
LBNL + Live