Baird North Wind — Project Summary

Queue ID
ERCOT-20INR0083
Capacity
350 MW
Technology
Wind
Status
active
Location
Callahan, TX
Region
ERCOT
Developer
BMP Wind, LLC
IA Status
IA Executed

Baird North Wind

ERCOT-20INR0083BetaActiveWindERCOTLBNL + Live

350 MW generation in Callahan, TX · In queue since May 2018 · Proposed COD December 2026

350 MW

Capacity

1

Components

Wind

7y 11m

In Queue

IA Executed

IA Status

Signed May 2019

Interconnection Timeline

Queue → IA

1 year

IA → COD

7y 7m

Total Duration

1 year

Construction75%
Queue EntryMay 4, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementMay 31, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2026-12-31

Project Details

State

TX

County

Callahan

Region

ERCOT

Developer

BMP Wind, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

68008 Latimer 345kV

Data Source

LBNL + Live

No news available for this project.