Castro Solar — Project Summary

Queue ID
ERCOT-20INR0050
Capacity
222.95 MW
Technology
Solar
Status
active
Location
Castro, TX
Region
ERCOT
Developer
Castro Solar One, LLC
IA Status
IA Executed

Castro Solar

ERCOT-20INR0050BetaActiveSolarERCOTLBNL + Live

222.95 MW generation in Castro, TX · In queue since February 2018 · Proposed COD September 2028

222.95 MW

Capacity

1

Components

Solar

8y 2m

In Queue

IA Executed

IA Status

Signed Nov 2020

Interconnection Timeline

Queue → IA

2y 9m

IA → COD

7y 10m

Total Duration

2y 9m

Construction75%
Queue EntryFeb 8, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementNov 30, 2020

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2028-09-20

Project Details

State

TX

County

Castro

Region

ERCOT

Developer

Castro Solar One, LLC

Utility

Entity

ERCOT

Service Type

Point of Interconnection

23912 Ogallala 345kV

Data Source

LBNL + Live

No news available for this project.