Siete — Project Summary

Queue ID
ERCOT-20INR0047
Capacity
375.06 MW
Technology
Wind
Status
active
Location
Webb, TX
Region
ERCOT
Developer
Apex Clean
IA Status
IA Executed

Siete

ERCOT-20INR0047BetaActiveWindERCOTLBNL + Live

375.06 MW generation in Webb, TX · In queue since October 2018 · Proposed COD January 2028

375.06 MW

Capacity

1

Components

Wind

7y 6m

In Queue

IA Executed

IA Status

Signed Jun 2022

Interconnection Timeline

Queue → IA

3y 8m

IA → COD

5y 7m

Total Duration

3y 8m

Construction75%
Queue EntryOct 23, 2018

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementJun 30, 2022

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–36 months

Commercial Operation

Proposed COD: 2028-01-03

Project Details

State

TX

County

Webb

Region

ERCOT

Developer

Apex Clean

Utility

Entity

ERCOT

Service Type

Point of Interconnection

345kV 8718 Triada

Data Source

LBNL + Live

No news available for this project.