Siete
ERCOT-20INR0047BetaActiveWindERCOTLBNL + Live
375.06 MW generation in Webb, TX · In queue since October 2018 · Proposed COD January 2028
375.06 MW
Capacity
1
Components
Wind
7y 6m
In Queue
IA Executed
IA Status
Signed Jun 2022
Interconnection Timeline
Queue → IA
3y 8m
IA → COD
5y 7m
Total Duration
3y 8m
Construction75%
Queue EntryOct 23, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementJun 30, 2022
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2028-01-03
Project Details
State
TX
County
Webb
Region
ERCOT
Developer
Apex Clean
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
345kV 8718 Triada
Data Source
LBNL + Live
No news available for this project.