Angus Solar
BetaActiveSolarERCOTLBNL
112 MW generation in Bosque, TX · In queue since November 2017 · Proposed COD April 2026
112 MW
Capacity
1
Components
Solar
8y 4m
In Queue
IA Executed
IA Status
Signed Dec 2021
Interconnection Timeline
Queue → IA
4y 1m
IA → COD
4y 4m
Total Duration
4y 1m
Construction75%
Queue EntryNov 13, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 6, 2021
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
TX
County
Bosque
Region
ERCOT
Developer
Angus Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 177 Bosque - 181 Cayote
Data Source
LBNL
No news available for this project.