Angus Solar — Project Summary

Queue ID
ERCOT-20INR0035
Capacity
112 MW
Technology
Solar
Status
active
Location
Bosque, TX
Region
ERCOT
Developer
Angus Solar, LLC
IA Status
IA Executed

Angus Solar

BetaActiveSolarERCOTLBNL

112 MW generation in Bosque, TX · In queue since November 2017 · Proposed COD April 2026

112 MW

Capacity

1

Components

Solar

8y 4m

In Queue

IA Executed

IA Status

Signed Dec 2021

Interconnection Timeline

Queue → IA

4y 1m

IA → COD

4y 4m

Total Duration

4y 1m

Construction75%
Queue EntryNov 13, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementDec 6, 2021

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2026-04-01

Project Details

State

TX

County

Bosque

Region

ERCOT

Developer

Angus Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

tap 138kV 177 Bosque - 181 Cayote

Data Source

LBNL

No news available for this project.