WILDWIND
ERCOT-20INR0033BetaActiveWindERCOTLBNL + Live
180.08 MW generation in Cooke, TX · In queue since October 2017 · Proposed COD April 2026
180.08 MW
Capacity
1
Components
Wind
8y 6m
In Queue
IA Executed
IA Status
Signed Feb 2020
Interconnection Timeline
Queue → IA
2y 4m
IA → COD
6y 2m
Total Duration
2y 4m
Construction75%
Queue EntryOct 18, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementFeb 21, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-04-15
Project Details
State
TX
County
Cooke
Region
ERCOT
Developer
Wildcat Creek
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 1730 KrumW - 2373 Anna
Data Source
LBNL + Live
No news available for this project.