Lutum Wind — Project Summary

Queue ID
ERCOT-20INR0029
Capacity
241.5 MW
Technology
Wind
Status
active
Location
Clay, TX
Region
ERCOT
Developer
RWE
IA Status
Facility Study

Lutum Wind

BetaActiveWindERCOTLBNL + Live

241.5 MW generation in Clay, TX · In queue since September 2017 · Proposed COD July 2027

241.5 MW

Capacity

1

Components

Wind

8y 6m

In Queue

Facility Study

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

9y 10m

Facilities Study50%
Queue EntrySep 12, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-07-01

Project Details

State

TX

County

Clay

Region

ERCOT

Developer

RWE

Utility

Entity

ERCOT

Point of Interconnection

tap 345kV 6101 Riley - 1730 W Krum

Data Source

LBNL + Live

No news available for this project.