Trinity Hills Wind repower
ERCOT-20INR0019BetaActiveWindERCOTLBNL + Live
— generation in Young, TX · In queue since July 2017 · Proposed COD April 2026
—
Capacity
0
Components
8y 9m
In Queue
IA Executed
IA Status
Signed Oct 2018
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
7y 6m
Total Duration
1y 3m
Schedule
0 months past proposed COD
Construction75%
Queue EntryJul 20, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 17, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-04-01
Project Details
State
TX
County
Young
Region
ERCOT
Developer
Trinity Hills Wind Farm LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
17002 Garvey Rd 345kV
Data Source
LBNL + Live
No news available for this project.