Lueders Solar
BetaActiveSolarERCOTLBNL + Live
40 MW generation in Haskell, TX · In queue since July 2017 · Proposed COD December 2028
40 MW
Capacity
1
Components
Solar
8y 8m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 5m
Facilities Study50%
Queue EntryJul 11, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-12-31
Project Details
State
TX
County
Haskell
Region
ERCOT
Developer
Innovative Solar 75
Utility
—
Entity
ERCOT
Point of Interconnection
Tap 138kV 6161 Paint Creek - 6200 Ft Phantom
Data Source
LBNL + Live
No news available for this project.