SP TX-12B Phase III
BetaActiveSolarERCOTLBNL + Live
40 MW generation in Upton, TX · In queue since September 2018 · Proposed COD December 2025
40 MW
Capacity
1
Components
Solar
7y 6m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
7y 3m
Schedule
4 months past proposed COD
Facilities Study50%
Queue EntrySep 12, 2018
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-02
Project Details
State
TX
County
Upton
Region
ERCOT
Developer
ConEd Development
Utility
—
Entity
ERCOT
Point of Interconnection
76040 Castillo 138kV
Data Source
LBNL + Live