SP TX-12B Phase III — Project Summary

Queue ID
ERCOT-19INR0189
Capacity
40 MW
Technology
Solar
Status
active
Location
Upton, TX
Region
ERCOT
Developer
ConEd Development
IA Status
Facility Study

SP TX-12B Phase III

BetaActiveSolarERCOTLBNL + Live

40 MW generation in Upton, TX · In queue since September 2018 · Proposed COD December 2025

40 MW

Capacity

1

Components

Solar

7y 6m

In Queue

Facility Study

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

7y 3m

Schedule

4 months past proposed COD

Facilities Study50%
Queue EntrySep 12, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-02

Project Details

State

TX

County

Upton

Region

ERCOT

Developer

ConEd Development

Utility

Entity

ERCOT

Point of Interconnection

76040 Castillo 138kV

Data Source

LBNL + Live

No news available for this project.