Shifting Gale Wind
BetaSuspendedWindERCOTLBNL
289 MW generation in Castro, TX · In queue since April 2018 · Proposed COD December 2025
289 MW
Capacity
1
Components
Wind
7y 11m
In Queue
Facility Study
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
7y 8m
Suspended50%
Queue EntryApr 26, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
TX
County
Castro
Region
ERCOT
Developer
SEAWAY WIND ENERGY LLC
Utility
—
Entity
ERCOT
Point of Interconnection
23912 Ogallala 345kV
Data Source
LBNL
No news available for this project.