Morrow Lake Solar — Project Summary

Queue ID
ERCOT-19INR0155
Capacity
201.1 MW
Technology
Solar
Status
active
Location
Frio, TX
Region
ERCOT
Developer
Morrow Lake Solar, LLC
IA Status
IA Executed

Morrow Lake Solar

BetaActiveSolarERCOTLBNL

201.1 MW generation in Frio, TX · In queue since December 2017 · Proposed COD January 2025

201.1 MW

Capacity

1

Components

Solar

8y 3m

In Queue

IA Executed

IA Status

Signed Aug 2019

Interconnection Timeline

Queue → IA

1y 8m

IA → COD

5y 5m

Total Duration

1y 8m

Schedule

14 months past proposed COD

Construction75%
Queue EntryDec 5, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.

Typical: 18–30 months (fastest major ISO)

Interconnection AgreementAug 29, 2019

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2025-01-25

Project Details

State

TX

County

Frio

Region

ERCOT

Developer

Morrow Lake Solar, LLC

Utility

Entity

ERCOT

Point of Interconnection

5895 Pearsall 138kV

Data Source

LBNL