Morrow Lake Solar
201.1 MW generation in Frio, TX · In queue since December 2017 · Proposed COD January 2025
201.1 MW
Capacity
1
Components
Solar
8y 3m
In Queue
IA Executed
IA Status
Signed Aug 2019
Queue → IA
1y 8m
IA → COD
5y 5m
Total Duration
1y 8m
Schedule
14 months past proposed COD
Interconnection request submitted to ISO/RTO
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Project under construction
Typical: 12–24 months
Proposed COD: 2025-01-25
State
TX
County
Frio
Region
ERCOT
Developer
Morrow Lake Solar, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
5895 Pearsall 138kV
Data Source
LBNL
Training Center students gain career insight at solar plant tour
PEARSALL — For students at the Training Center of Central Texas, a visit to Leeward Renewable Energy's Morrow Lake Solar Power Plant was...
Training Center students gain career insight at solar plant tour
PEARSALL — For students at the Training Center of Central Texas, a visit to Leeward Renewable Energy's Morrow Lake Solar Power Plant was...
Ampion energizes 5 new community solar sites in Maine | Projects Weekly
Five new community solar sites are up and running in Maine. Leeward Renewable Energy completed a 200 MW project in Texas.
LRE Commences Commercial Operations of Morrow Lake Solar in Texas
LRE (Leeward Renewable Energy) today announced the completion and commercial operation of its 200-megawatt (MW) Morrow Lake Solar project.