Roadrunner Crossing Wind SLF
BetaActiveWindERCOTLBNL
128 MW generation in Eastland, TX · In queue since September 2017 · Proposed COD January 2025
128 MW
Capacity
1
Components
Wind
8y 6m
In Queue
IA Executed
IA Status
Signed Apr 2020
Interconnection Timeline
Queue → IA
2y 7m
IA → COD
4y 9m
Total Duration
2y 7m
Schedule
14 months past proposed COD
Construction75%
Queue EntrySep 8, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementApr 17, 2020
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2025-01-31
Project Details
State
TX
County
Eastland
Region
ERCOT
Developer
Roadrunner Crossing Wind Farm, LLC
Utility
—
Entity
ERCOT
Point of Interconnection
68051 Reata 345kV
Data Source
LBNL
No news available for this project.