Prairie Hill Wind
ERCOT-19INR0100BetaActiveWindERCOTLBNL + Live
300 MW generation in Mclennan, TX · In queue since June 2017 · Proposed COD September 2027
300 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
Signed Sep 2018
Interconnection Timeline
Queue → IA
1y 3m
IA → COD
9 years
Total Duration
1y 3m
Construction75%
Queue EntryJun 19, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementSep 17, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2027-09-30
Project Details
State
TX
County
Mclennan
Region
ERCOT
Developer
Prairie Hill LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
tap 345kV 3405 Tradinghouse - 3402 Lake Creek
Data Source
LBNL + Live
No news available for this project.