Whitehorse Wind
ERCOT-19INR0080BetaActiveWindERCOTLBNL + Live
418.9 MW generation in Fisher, TX · In queue since June 2017 · Proposed COD December 2026
418.9 MW
Capacity
1
Components
Wind
8y 10m
In Queue
IA Executed
IA Status
Signed Dec 2018
Interconnection Timeline
Queue → IA
1y 6m
IA → COD
8 years
Total Duration
1y 6m
Construction75%
Queue EntryJun 23, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 5, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Fisher
Region
ERCOT
Developer
MESQUITE STAR SPECIAL LLC
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
68001 Clayton 345kV
Data Source
LBNL + Live