Horseshoe Bend Solar
BetaActiveSolarERCOTLBNL + Live
301.1 MW generation in Brown, TX · In queue since June 2017 · Proposed COD February 2027
301.1 MW
Capacity
1
Components
Solar
8y 9m
In Queue
Facility Study
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
9y 8m
Facilities Study50%
Queue EntryJun 23, 2017
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-02-20
Project Details
State
TX
County
Brown
Region
ERCOT
Developer
Clenera
Utility
—
Entity
ERCOT
Point of Interconnection
1444 Brown 345kV
Data Source
LBNL + Live
No news available for this project.