San Bernard Solar
BetaSuspendedSolarERCOTLBNL
100 MW generation in Wharton, TX · In queue since January 2017
100 MW
Capacity
1
Components
Solar
9y 2m
In Queue
Facility Study
IA Status
Interconnection Timeline
Total Duration
9y 2m
Suspended50%
Queue EntryJan 26, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Project Details
State
TX
County
Wharton
Region
ERCOT
Developer
Sunchase Power
Utility
—
Entity
ERCOT
Point of Interconnection
tap 138kV 43012 New Gulf - 43340 Texas Gulf Sulphur
Data Source
LBNL
No news available for this project.