Holstein 2 Solar
BetaActiveSolarERCOTLBNL + Live
101.7 MW generation in Nolan, TX · In queue since December 2016 · Proposed COD April 2028
101.7 MW
Capacity
1
Components
Solar
9y 3m
In Queue
Facility Study
IA Status
COD target: 2028
Interconnection Timeline
Total Duration
11y 4m
Facilities Study50%
Queue EntryDec 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2028-04-03
Project Details
State
TX
County
Nolan
Region
ERCOT
Developer
229HD 8me LLC
Utility
—
Entity
ERCOT
Point of Interconnection
11406 Central Bluff 345kV
Data Source
LBNL + Live
No news available for this project.