Sweetwater 1 repower
ERCOT-18INR0073BetaActiveWindERCOTLBNL + Live
3 MW generation in Nolan, TX · In queue since February 2018 · Proposed COD November 2024
3 MW
Capacity
1
Components
Wind
8y 2m
In Queue
IA Executed
IA Status
Signed Oct 2002
Interconnection Timeline
IA → COD
22y 1m
Total Duration
8y 2m
Schedule
16 months past proposed COD
Construction75%
Queue EntryFeb 9, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementOct 23, 2002
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2024-11-30
Project Details
State
TX
County
Nolan
Region
ERCOT
Developer
Leeward Energy
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
71050 Bitter Creek 345kV
Data Source
LBNL + Live
No news available for this project.