Indian Mesa repower
ERCOT-18INR0069BetaActiveWindERCOTLBNL + Live
9.3 MW generation in Pecos, TX · In queue since May 2018 · Proposed COD December 2026
9.3 MW
Capacity
1
Components
Wind
7y 11m
In Queue
IA Executed
IA Status
Signed Dec 2018
Interconnection Timeline
Queue → IA
7 months
IA → COD
8 years
Total Duration
7 months
Construction75%
Queue EntryMay 22, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
ERCOT uses a serial "connect and manage" approach — fastest among major ISOs.
Typical: 18–30 months (fastest major ISO)
Interconnection AgreementDec 4, 2018
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Proposed COD: 2026-12-31
Project Details
State
TX
County
Pecos
Region
ERCOT
Developer
Nextera
Utility
—
Entity
ERCOT
Service Type
—
Point of Interconnection
76019 Indian NWP 138kV
Data Source
LBNL + Live
No news available for this project.